How to load MS Project .mpp file to p6

Rama Krishna NalajalaMember for 10 years 7 months
Created
1
18
0

I have a schedule  done in MS Project thats in .mpp format. I tried to load the schedule into p6 but it accepts only XML. I converted the file format to XML but of no use. Could anyone shed a light on how to load this into p6

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    convert the mpp to an mpx

    convert the mpp to an mpx there are several converters on the internet. Then import the mpx file