Cost Loading at Late Stage of Project

Leith KaouasMember for 12 years 5 months
Created
0
3
0

Hi all,

I was just asked to cost load P6 for a project that has been running already for 3 years..30,000+ activities..

I started by assigning in a cash resource the remaining $ (Contract BOQ $ - Actual to Date $) for each activity and the % is calculated based on site progress %, however this is way too time consuming.

The manpower is minimal for this task, any ideas on how to approach this task?