Cost Loading at Late Stage of Project
In the Open Standard
Leith KaouasMember for 12 years 5 months
- Created
- 0
- 3
0
Hi all,
I was just asked to cost load P6 for a project that has been running already for 3 years..30,000+ activities..
I started by assigning in a cash resource the remaining $ (Contract BOQ $ - Actual to Date $) for each activity and the % is calculated based on site progress %, however this is way too time consuming.
The manpower is minimal for this task, any ideas on how to approach this task?
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?