Budgeted cost extends beyond the project finish date.
In the Open Standard
Renjith RCMember for 16 years 3 months
- Created
- 1
- 3
0
Hi everybody
I have a problem with one of my program (Updated Program), I want to use it as a revised baseline. The issue is project finish date is 24-Jan-2019,
but when i check the activity usage spreadsheet, Cost loaded in the Preliminaries activity (LEVEL OF EFFORT) is extending upto MAR 2019. Cost is loaded as expense based on the requirement from the client.
Preliminaries activity is using a 7 days calendar
Activity Type is LEVEL OF EFFORT
Duration Type is Fixed Duration & Units
% Complete Type is PHYSICAL
1 reply
Oldest firstLog in or join to reply