Setting Up a New Project
In the Open Standard
H L-ajMember for 9 years 6 months
- Created
- 1
- 3
0
I am returning to P6 after some time away and would like to ensure I am setting up my project accurately. Based on estimates, I need budgeted labour units (man hours) to be fixed and durations to be automatically generated based on the aforementioned manhours. I have used resource dependent activity type and fixed units for duration type. Is this correct? Budgeted labour units change when i attempt resource loading and I obviously do not want that :) Any help is warmly welcomed / greatly appreciated!