Hello every one, 

how can i calculate the construction delay taking in account that the construction isn't finished yet?

Regards.

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    the delay is when it was

    the delay is when it was originally planned to finish - when it is forecated to finish

    original completion date December 15, 2018

    current completion date Jnauary 15, 2019

    Delay - 31 calendar days 

  2. 0
    Kathy Castle ·

    Are you asking techniques

    Are you asking techniques related with construction delay analysis ? 

  3. 0
    Zoltan Palffy ·

    you stays will tell you that

    you stays will tell you that based on where you should be and where you actually are