Project Driving Other Project

Philip JamesMember for 10 years 7 months
Created
3
26
0

Is it possible to 'turn off' one project driving another project on the same node?

I have tried to make one project inactive. Without any joy....

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    its bascially all reated

    its bascially all reated projects or none

    go to tools schedule

    click on the options button 

     at the top uncheck  ignore relationships to and from other projects 

  2. 0
    Philip James ·

    Hi ZoltonThank you, thats

    Hi Zolton

    Thank you, thats what I thought

     

    Philip

  3. 0
    Zoltan Palffy ·

    glad I could help

    glad I could help 