Skip to content

What to do with your project during COVID-19?

Sam WoodsMember for 6 years 7 months
Created
2
3
0

How would you answer this question? I encountered it in  this <a href="https://www.erudicat.com/covid-19-question-1050">PMP Exam Simulator</a>

Question:

 "You are managing a project to combine video clips for a commercial video for your client. There are many specific requirements as to the color grading and audio. The most talented employees from your company are in your team since this project is major and is expected to bring the most profit this and next year. Three weeks ago during the morning meeting, you have been informed by one of the team members that a complex problem arose. This problem could have an extremely negative impact on the project. You decided to analyze the problem right away using a fishbone diagram to define the cause of the problem. Then you identified a solution and implemented this solution. Today you received am email from the same team member who informed you the the same problem resurfaced. Which of the following things you most likely forgot to do?",

   

                "A" : "Get approval from the sponsors.",

                "B" : "Confirm that the solution actually solved the problem.",

                "C" : "Use a Pareto chart.",

                "D" : "Identify the reason why the problem occurred."

            

     

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    First thing that you do when

    First thing that you do when an unplanned event occurs you immediately update the schedule so that you know exactly what is done what is partially done and what has not started

    Next I would modify my calendars and make the shutdown period all non working days. This will prevent any work from happening during this time frame.

     When you restart your project you will have to add some restart up time because you will not be at the same level of manpower, equipment or material as you were when you shut down. You may have to adjust time for procurement ie steel was in an order in a mill and now you are in a different order.

    Yes for not a total job shutdown then create a separate calendar for each trade.

    This is force majoure situation so it will be time but no money classified as a non compensable time extension

    Create a separate cost code for this and also see if your insurance or bonding company will cover any of the added costs.

    If you need to adjust durations due to lack of manpower

     

    You have 2 options

    Option #1 

    Keep the original duration and make the remaining duration greater than the original duration 

    Option #2

    Create a udf and run a global change and make the udf equal to the original duration then increase the original duration for the reduced manpower

    In both options create a new activity. Code and tag each activity that you have changed the original duration or remaining duration due to reduced manpower 

    Once you have the code you can group these activities by the new code that you added

    You can then see if any of these are on the critical path

    Also since you have created this code you can give these activities a different color and or cross hatch them.

    What you can do is go ahead and create a resource call it lumpsum and assign it to every activity that involves labor (not procurement or submittals) and it will take 8 (for 8 hours per day) and it will multiply it by the duration to give you your manpower.

    I.e. 5 days * 8 hrs/day= 40 manhours which is 1 man per day for 5 days.

    This is your minimum total manpower required on the project 

    Notebook logs are good but are not sortable 

    You can also create commodity curves 

    I.e. drywall installation Planned number of square feet per day or per week Then track actual installation against the planned.

    You can do this for critical activities or major commodities.

    Write a narrative each day from the previous day as it relates to the schedule. Not a typical daily report.

  2. 0
    Ozan Turkyilmaz ·

    Hello, I'll say "B" :

    Hello,

     

    I'll say "B" : "Confirm that the solution actually solved the problem."

    Reoccrance may be related to the unsolved problem.

     

    Regards,

    Ozan

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?