Logic?

Paul SpiceMember for 25 years 4 months
Created
4
2
0
Is there a way in P3 to have a task scheduled by saying, "Start date of this task is finish-start to when the first two of the following five tasks have been completed?"

This is required for production logic when step two of a process requires two batches of intermediate product from 5 batch plants. The 5 batch plants are independent, so the second process can start when any two are complete.

4 replies

Oldest first
  1. 0
    Ali Hamouda ·

    Reply to Logic

    Hi,

    As I understand , you have a Conditioned Link.

    Suppose activities B,C,D,E,F two of them need to be linked to activity A Just when any two of them has been completed.

    To translate the upmentioned statement into Logic fomula:

    1-First of all export your program to excel format.the format should have at least the fields"ID,percent progres,Predecessor"

    2-in the field of the predecessor you will write for each of the five activities the fomula with if statment"IF %Progress=100 Predecessor=FS".

    3-you will need to know how to link Exel files to Primavera.othrewise you will import the file back again to P3 each time you update your progress.

  2. 0
    Paul Spice ·

    Linking

    Hi Ali,

    That is a good idea, but will only work when two activities are 100% complete. How do I link them for forecasting, which means when the first two are scheduled to be completed, the "A" can proceed?

    If B,C,D, or E early starts change due to updatiing how can "A" link itself to the first two of them in early start sequence?
  3. 0
    James Williams ·
    Hi Paul,

    I seem to remember having asked P3 about this one a while back. They had no real answer that could solve the problem, other than by some means of regular "physical" checking of the network, and by adding a logic link at the appropriate time.

    Sorry, its not the answer your looking for.

    Regards...James
  4. 0
    Paul Spice ·
    Dear James,
    Thats what Im doing now, physically checking the pred start dates and linking the succs manually to the first two.
    I think thats the only way, thanks,
    Paul.