Retained Logic Question

Sunil KumarMember for 21 years 6 months
Created
3
2
0
Frank,

The problem I have is when I schdeule on retained logic, I have some activities which has completed 90% and will take actually one day after the schedule date but when I schedule it shows it requires more than 1 day and all its predecessor is 100% complete.

Trust I was clear on this


Thanx

Sunil

3 replies

Oldest first
  1. 0
    Frank Borcherdt ·
    Check constraints, suspend and resume dates and calendar of 90% complete activity.

    If using Projects within Project Groups check advanced scheduling options re Data dates.

    There has to be a logical reason and I consider progress overide fairly dangerous for the reason I explained before.
  2. 0
    Ernesto Puyana ·
    It could be that your program is linking percent complete to remaining duration.
  3. 0
    Bernard Ertl ·
    Sunil, perhaps it may be a calendar phase problem. Check the calendars for any FF predecessors (I suppose ancestors is a better word - you may have to check several tasks preceding) to see if they are delaying the task (even though the predecessor is completed).

    I remember seeing this problem on some scheduling system back when I was doing some testing, but I honestly don’t recall which system exhibited this behavior.

    Bernard Ertl
    eTaskMaker Project Planning Software

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?