Retained Logic Question
In the Open Standard
Sunil KumarMember for 21 years 6 months
- Created
- 3
- 2
0
Frank,
The problem I have is when I schdeule on retained logic, I have some activities which has completed 90% and will take actually one day after the schedule date but when I schedule it shows it requires more than 1 day and all its predecessor is 100% complete.
Trust I was clear on this
Thanx
Sunil
The problem I have is when I schdeule on retained logic, I have some activities which has completed 90% and will take actually one day after the schedule date but when I schedule it shows it requires more than 1 day and all its predecessor is 100% complete.
Trust I was clear on this
Thanx
Sunil