Hi Planners

Total float for activities dont reflect correct picture while we use progress override option in scheduling. Why is this so, can anyone pls explain.

Regards
Ranish

3 replies

Oldest first
  1. 0
    Forum Guest ·
    Ranesh, This might help you as a reference, pls. visit this web address- http://www.pmicos.org/cgi-bin/ubb/ultimatebb.cgi?ubb=get_topic;f=4;t=000003
  2. 0
    Forum Guest ·
    Hi guest member,
    Thankyou very much for the site, I have registered and made a comment on the topic.
    Ranish
  3. 0
    Jorge Taguinod ·
    Total float computation will be different for progress override and retained logic. Both will be correct, depending on your perspective.

    The problem here is that you can only set one option to apply to ALL activities. It would have been nicer to apply different options to different activities.

    So, with the current state of things, you need to decide which one to use. Retained logic gives you a more conservative projection of how things are going to be. So if you want to be on the safer side, user retained logic.

    Jorge
    Crown Systems (Philippines)

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?