P3 e issues

Sathish KumarMember for 23 years 6 months
Created
2
1
0
The scheduled percentage is showing false figures in P3e. Can any one help me to resolve this issue.

Another issue i am facing with P3e is the usage of negative lags for which the early finish & late finish calculations shows error of 1 day.Have anyone faced this problem .Please advise me if u have a solution.

2 replies

Oldest first
  1. 0
    Naveed Tariq, PE, PMP ·
    We had the same problem in ver 3.5, but updating our liscence to ver 4.0 resolved the issue.

    Cheers
  2. 0
    Ronald Winter ·
    If you have any other comments to add, please put them in the P3e section and not this one. - The Moderator