Planned Value Management
In the Open Standard
Yves TrudelMember for 21 years 2 months
- Created
- 2
- 1
0
I have problem with planned value curve management.
Current project data is as follows:
Data Date: Feb 10, 2006
Total BQ: 4,574,089 hrs
Earned Value: 602,470 hrs
Planned Value: at DD= 901,121hrs
Planned Value Curve: 4,448,034 hrs
Target Project data is:
Data Date: Nov 10, 2005
Total BQ: 4,573,326 hrs
Earned Value: 293,549
How come I dont get 4,573,326 hrs for planned value instead of 4,448,034 hrs?
I understand pretty much how I get the planned value at Data Date, but I cannot figure how P3 calculates the remainder.
Thank you in advance for your help
Yves Trudel
Current project data is as follows:
Data Date: Feb 10, 2006
Total BQ: 4,574,089 hrs
Earned Value: 602,470 hrs
Planned Value: at DD= 901,121hrs
Planned Value Curve: 4,448,034 hrs
Target Project data is:
Data Date: Nov 10, 2005
Total BQ: 4,573,326 hrs
Earned Value: 293,549
How come I dont get 4,573,326 hrs for planned value instead of 4,448,034 hrs?
I understand pretty much how I get the planned value at Data Date, but I cannot figure how P3 calculates the remainder.
Thank you in advance for your help
Yves Trudel
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?