Actual earned quantity!! Not match with real situation!
In the Open Standard
Santhosh kumar NarayananMember for 20 years 2 months
- Created
- 2
- 1
0
Hi,
Iam facing a problem. In my program i loaded concrete qty with resurce lag (exp. activity concrteing of slab of 23 days duration 22 days lag and last 1 day conc)while loading buget qty.
When i compare with planned curve and actual curve form p3. Actual shows inaccurate figure ( Exp. i strted activity 30 days back due to some problem it got delayed but we finished 40 % for concrete - keep in mind not concrete just form and steel we need another 5 days to complete) but whn you take resource laoding from updated schedule it give 40 % value, if fact concrete with do after 5 days only what to do.
Iam facing a problem. In my program i loaded concrete qty with resurce lag (exp. activity concrteing of slab of 23 days duration 22 days lag and last 1 day conc)while loading buget qty.
When i compare with planned curve and actual curve form p3. Actual shows inaccurate figure ( Exp. i strted activity 30 days back due to some problem it got delayed but we finished 40 % for concrete - keep in mind not concrete just form and steel we need another 5 days to complete) but whn you take resource laoding from updated schedule it give 40 % value, if fact concrete with do after 5 days only what to do.
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?