Actual earned quantity!! Not match with real situation!

Santhosh kumar NarayananMember for 20 years 2 months
Created
2
1
0
Hi,
Iam facing a problem. In my program i loaded concrete qty with resurce lag (exp. activity concrteing of slab of 23 days duration 22 days lag and last 1 day conc)while loading buget qty.

When i compare with planned curve and actual curve form p3. Actual shows inaccurate figure ( Exp. i strted activity 30 days back due to some problem it got delayed but we finished 40 % for concrete - keep in mind not concrete just form and steel we need another 5 days to complete) but whn you take resource laoding from updated schedule it give 40 % value, if fact concrete with do after 5 days only what to do.

2 replies

Oldest first
  1. 0
    Mk Tse ·
    Instead of resource lag, please consider the resource curve. I create one for concrete - 0% to whole period except the last one. So the curve is "flat" except the last day.

    So no actual quantity until the concrete day and same day for the Actual Finish of this activity.
  2. 0
    Alex Wong ·
    Check your autocost rule as well

    BTW as .mktse suggested, seperate your activity and resources that will help to untangle the mess

    Alex