P3 Planned vs actual

Desmond MitchellMember for 19 years 7 months
Created
1
1
0
I need to create an Scurve reporting on my Planned and actual % complete with my data date line

On my activity chart, after i update my progress i need to see my target % complete for that particular data date.
I want see what was planned for that particular day and what was my actual because i need to establish whether i am ahead or behind or on target

1 reply

Oldest first
  1. 0
    Bijaya Bajracharya ·
    P3 makes S curve from resource data. So the first question to you is whether your programme is resource loaded?

    I know you are just trying to compare planned percent complete vs actual percent. But the "percent complete" on its own can mean a lot of things to lot of people. And as for S curves in P3, percent complete is derived either from units or costs of the resources.