leveling type

Pinan T.Member for 19 years 2 months
Created
1
1
0
i cannot assign the leveling type stretch, and crunch to an activity...is it because i do not have normal and maximum resource rate or my P3 has a problem?i can assign it by gchange but it does not appear in act column LTYP..up to split type only

1 reply

Oldest first
  1. 0
    Paul Harris ·
    The activity type needs to be independent and resources driving before this option will work.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au