Skip to content

Budgeted cost does not match with generated cash flow

Albert BalogoMember for 18 years 4 months
Created
3
4
0
Hi to All,

!. Any body can help me, using P3 version 3.1 I’ve loaded the budgeted cost (Selling cost of project) for each activity, but the problem is, when i trying to run for monthly cashflow the generated output could not match to the budgeted cost it’s exceeding almost 10% of total budgeted cost.

2.(Budgeted cost)-(Cost to date) = Cost to complete..... these three was loaded to my program but the amount of cost to complete has wrong output most of the activity.

Thank you

Albert

3 replies

Oldest first
  1. 0
    Anoon Iimos ·
    have you chosen "costs" as your weighting factor before running your schedule? how do you update your schedule?
  2. 0
    Albert Balogo ·
    Yes Anoon, there is three ways on how to update the program duration,resources and cost. these three i used cost. even my friend he’s a planner too, he cant resolve this problem. you can try it to your program, just let me know if something remedy.

    thanks
  3. 0
    Anoon Iimos ·
    i’m talking of "weighting factor", if you had used "costs" you must update your program with costs, and not with any other options.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?