In P3e is there a way to read PLANNED % VARIANCE in a report, I’ve tried a few global changes but with no success

any help would be appreciated.
thanks
Richard.

1 reply

Oldest first
  1. 0
    Alex Wong ·
    Richard

    You can display the column call Plan Variance.

    HTH

    Alex