Benchmark schedule for resource leveling test
- Created
- 11
- 3
Vladimir,
I tried the Asta Powerproject on what I call for myself a “Vladimir Liberzon resource leveling test”. A simple schedule with 2 resources and 4 tasks, which you showed in one of the forums here. I just found it very illustrative for the purpose of testing resource leveling intelligence of a tool
Powerproject did not pass this test, as well as Microsoft Project doesn't, but I noticed, that Spider also passes it only starting from “Optimization” Method and does not pass with Standard and Advanced method
Question: Do you have an example of a schedule, which shows different results for all 4 methods, available in Spider professional, just to demonstrate how resource constrained scheduling intelligence increases (and schedule duration presumably decreases) with advance of a scheduling Method used (and with advance of a Spider version price, where this Method is availble)?
Regards.
Evgeny
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?