Externally

2 coats sandtex etc - to render/concrete 2.50 m2/hr - to brick/blockwork 2.00 m2/hr 1 sealer, 2 emulsion - to render/concrete 2.00 m2/hr - to brick/blockwork 1.70 m2/hr
Externally entries
ActivityEntry (verbatim)ValueSource
BrickworkOutput 25m2 per man week overall facing brickwork25 m2 per man weekper man weekParsedBrickwork

1–1 of 1