Rates, Norms & Durations / Fitout & Finishes / Painting & Decorations
Walls
2 entriesSource page: Walls
Subjects on this page
| Activity | Entry (verbatim) | Value | Source |
|---|---|---|---|
| BrickworkExternally | Output 25m2 per man week overall facing brickwork | 25 m2 per man weekper man weekParsed | Brickwork |
| Internally | 2 coats emulsion - to plaster 8.00 m2/hr - to brick/blockwork 6.00 m2/hr 1 mist, 2 emulsion - to plaster 6.00 m2/hr - to brick/blockwork 4.50 m2/hr 1 primer, 1 undercoat, 1 gloss - to plaster 2.30 m2/hr Undercoat - to door frame 20.00 m/hr Gloss - to door frame 16.50 m/hr Undercoat - to door 7.14 m2/hr Gloss - to door 6.25 m2/hr9 rate statements found; left for an editor | — | Internally |
1–2 of 2
These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.