Rates, Norms & Durations
Externally
In the Open Standard
2 coats sandtex etc - to render/concrete 2.50 m2/hr - to brick/blockwork 2.00 m2/hr 1 sealer, 2 emulsion - to render/concrete 2.00 m2/hr - to brick/blockwork 1.70 m2/hr
Started by Oliver Melling ·
- Last updated
- Updated
- Views
- 6 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →
2 coats sandtex etc
- to render/concrete 2.50 m2/hr
- to brick/blockwork 2.00 m2/hr
1 sealer, 2 emulsion
- to render/concrete 2.00 m2/hr
- to brick/blockwork 1.70 m2/hr