Rates, Norms & Durations / Building & Construction / Roofs & Waterproofing
Flat & Layered Roofs
2 entriesSource page: Flat & Layered Roofs
Subjects on this page
| Activity | Entry (verbatim) | Value | Source |
|---|---|---|---|
| Asphalt Roofs | Asphalt Roofs Usually carried out with a 2 man gang with an additional 1 or 2 labourers. A typical composite rate of 45 m2/day | 45 m2 per dayper dayParsed | Asphalt Roofs |
| Felt Roofs | Built-Up Felt Roofs Usually carried out with a minimum of a 1 man gang with a labourer. Large Roof Areas = 52 m2/day Smaller or Complicated Areas = 35 m2/day2 rate statements found; left for an editor | — | Felt Roofs |
1–2 of 2