Roofs & Waterproofing

Roofs & Waterproofing entries
ActivityEntry (verbatim)ValueSource
Aluminium RoofingMetal Roof DeckingAluminium Roofing Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Flat Roof Aluminium Work = 2.8 m2/day Sloping Roof Aluminium Work = 1.9 m2/day2 rate statements found; left for an editor—Aluminium Roofing
Asbestos Roofs Sheeted RoofsAsbestos Type Roofs A typical rate of 39 m2/day39 m2 per dayper dayParsedAsbestos Roofs
Asphalt RoofsFlat & Layered RoofsAsphalt Roofs Usually carried out with a 2 man gang with an additional 1 or 2 labourers. A typical composite rate of 45 m2/day45 m2 per dayper dayParsedAsphalt Roofs
Copper RoofingMetal Roof DeckingMetal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Copper Roofing Flat Roof Copper Work = 3.0 m2/day Sloping Roof Copper Work = 2.7 m2/day2 rate statements found; left for an editor—Copper Roofing
Felt RoofsFlat & Layered RoofsBuilt-Up Felt Roofs Usually carried out with a minimum of a 1 man gang with a labourer. Large Roof Areas = 52 m2/day Smaller or Complicated Areas = 35 m2/day2 rate statements found; left for an editor—Felt Roofs
Gravel ChippingsThermal & Moisture ProtectionRoof Protections Gravel & Chippings - Allow a rate of 1.4 tonnes/day for transporting and laying out solar reflective chippings.1.4 t per dayper dayParsedGravel Chippings
Guttering & PipesRainwater WorksDownPipes 75 mm UPVC Pipes 3.3 m/hr 75 mm Cast Iron Pipes 2.1 m/hr 72 mm Aluminium Pipe System 2.5 m/hr Guttering 75 mm UPVC Gutter 3.1 m/hr 75 mm Cast Iron Gutter 2.5 m/hr 72 mm Aluminium Gutter System 2.9 m/hr Fittings A composite rate has been calculated to be used as an extra-over basis for all pipe fittings etc. 75 mm UPVC Fittings 3.1 no/hr 75 mm Cast Iron Fittings 2.2 no/hr 72 mm Aluminium Fittings 1.9 no/hr9 rate statements found; left for an editor—Guttering & Pipes
Lead RoofingMetal Roof DeckingMetal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Lead Roofing Flat Roof Lead Work = 2.5 m2/day Sloping Roof Lead Work = 2.1 m2/day2 rate statements found; left for an editor—Lead Roofing
Metal DeckingMetal Roof DeckingMetal Decking SystemsUsually carried out with a minimum of a 3 man gang with a labourer.Large Roof Areas = 70 m2/daySmaller or Complicated Areas = 28 m2/dayMetal DeckingTask / DescriptionSlow Ave Fast Units Metal Decking, large areas- 70.0 - m2/day Metal Decking, small or complicated- 28.0 - m2/day Titanium Sheeted Roofs- 9.5 - m2/day Copper Roofs, flat work- 3.0 - m2/day Copper Roofs, sloping work- 2.7 - m2/day Zinc Roofs, flat work- 2.4 - m2/day Zinc Roofs, sloping work- 2.1 - m2/day Aluminium Roofs, flat work- 2.8 - m2/day Aluminium Roofs, sloping work- 1.9 - m2/day Lead Roofs, flat work- 2.5 - m2/day Lead Roofs, sloping work- 2.1 - m2/day Lead Roofs, dormer cheeks- 1.3 - m2/day Lead Roofs, flat gutters- 88.0 - m/day Lead Roofs, flat copings- 76.0 - m/day Lead Roofs, stepped gutters- 3.5 - m/day Lead Roofs, shaped copings- 3.3 - m/day Lead Roofs, cover step flashings- 3.2 - m/day Lead Roofs, rooflight flashings- 0.8 - no/day Lead Roofs, domed roof coverings- 0.7 - m2/day2 rate statements found; left for an editor—Metal Decking
Metal FeaturesMetal Roof DeckingMetal Roof Features Composite rates have been calculated to provide an approximation of the time elements for these ancillary parts to metal roofs. Dormer Cheeks 1.36 m2/day Flat Gutter & Coping Flashings negligible time Step Gutter & Shaped Copings 3.50 m/day Cover Step Flashings 3.20 m/day Roof Light Flashing 0.80 no/day Dome Structures 0.75 m2/day5 rate statements found; left for an editor—Metal Features
P.V.C. SheetingThermal & Moisture ProtectionP.V.C. Sheeting Usually carried out with a minimum of a 3 man gang with a labourer. Large Roof Areas = 50 m2/day Smaller Areas = 40 m2/day2 rate statements found; left for an editor—P.V.C. Sheeting
Polythene Waterproofing Thermal & Moisture ProtectionPolythene Sheeting Sheet materials (DPC/DPM's etc) fixed to prepared concrete surfaces. Horizontal Surfaces = 20.0 m2/hr20 m2 per hrper hrParsedPolythene Waterproofing
Profiled SheetingSheeted RoofsProfiled Sheeting Systems Usually carried out with a minimum of a 2 man gang. Large Roof Areas = 54 m2/day54 m2 per dayper dayParsedProfiled Sheeting
Roof InsulationPolystyrene Boarding Expanded Polystyrene Boards 8.55 m2/hr Glass Fibre Wool Fix 50 mm Rocksil between joists Low Pitch Roof 12.00 m2/hr Normal Pitch Roof 19.00 m2/hr3 rate statements found; left for an editor—Roof Insulation
Roof Lights—Roof Lights
Sheeted RoofsSheeted RoofsSheeted RoofsTask / DescriptionSlow Ave Fast Units PVC Sheeted Roofs, large areas- 50.0 - m2/day PVC Sheeted Roofs, small areas- 40.0 - m2/day Plastic Profiled Sheet Systems- 54.0 - m2/day—Sheeted Roofs
Slate RoofsTiled RoofsSlate Roofs Usually carried out with a 2 man gang, sometimes with an additional labourer. Natural Welsh Slate 3.5-5 mm thick 18.0 m2/day Natural Cumbrian 8-11 mm thick 8.5 m2/day Asbestos Slates 36.0 m2/day3 rate statements found; left for an editor—Slate Roofs
Tiled RoofsTiled RoofsUsually carried out with a 2 man gang with 1 labourer. The rates include for felting, battening and fixing of tiles etc. Concrete Interlocking Tiles 52 m2/day Clay Pan Tiles 26 m2/day2 rate statements found; left for an editor—Tiled Roofs
Titanium RoofingMetal Roof DeckingTitanium Roofing System Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Titanium roof on multiple sub‑layers. Typical composite rate of 9.5 m2/day. Installation Typical timing and sequence of works. This is for an order of 5,000 m2 (HK Station Upper & Lower Roofs)... Element Week Manpower Temporary Works 0 - 2 5 Metal Decking 2 - 3 12 Gutter Subframe 3 - 6 6 Vapour Barrier 4 - 13 4 Rockwool 4 – 13 44 Cement Board 4 – 13 6 Ice / Water Shield 4 – 13 4 Gutter Lining 6 - 9 4 Aluminium Cladding / Subframe 6 – 11 6 Titanium Cladding 8 – 17 17 Aluminium Pannelling 9 - 14 69.5 m2 per dayper dayParsedTitanium Roofing
WaterproofingTask / DescriptionSlow Ave Fast Units Asphalt coatings, horizontal surfaces3.5 4.2 5.8 m2/hr Asphalt coatings, vertical surfaces1.2 1.7 2.2 m2/hr Bituminous Brushed application, 2 coats4.8 5.0 6.3 m2/hr Bituminous Brushed application, 3 coats3.3 3.5 4.4 m2/hr Bituminous Sheets, horizontal surfaces3.8 4.0 4.8 m2/hr Bituminous Sheets, vertical surfaces3.3 3.5 4.2 m2/hr Polythene Sheets, horizontal surfaces- 20.0 - m2/hr Bentonite Sheets, horizontal surfaces18.7 25.0 31.3 m2/hr Bentonite Sheets, vertical surfaces11.2 15.0 17.3 m2/hr Epoxy Based application, 1 coat- 75.0 - m2/hr Epoxy Based application, 2 coat- 38.0 - m2/hr8 rate statements found; left for an editor—Waterproofing
Zinc RoofingMetal Roof DeckingZinc Roofing Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Flat Roof Zinc Work = 2.3 m2/day Sloping Roof Zinc Work = 1.9 m2/day2 rate statements found; left for an editor—Zinc Roofing

1–21 of 21

These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.