Post Tensioning Works

Post Tensioning Works entries
ActivityEntry (verbatim)Source
Post TensioningConcrete - Post Tensioning Sequence:Concrete poured 1st Bay.After 48 hrs concrete is stressed to initial strength (15 kN takes 1 day).5 days after initial stressing, concrete is stressed to final strength (30 kN takes 1 day).Formwork may now be struck and adjacent bay poured.Post TensioningTask / DescriptionSlow Ave Fast Units Lag for Initial Stress Tensioning after 1st bay cast- 48.0 - hrs Lag for Final Stress Tensioning after Initial Stress- 120.0 - hrsPost Tensioning

1–1 of 1

These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.