Rainwater Works
Rainwater WorksTask / DescriptionSlow Ave Fast Units UPVC Downpipes, 75mm- 3.3 - m/hr UPVC Guttering, 75mm- 3.1 - m/hr UPVC RWP Fittings, 75mm- 3.1 - no/hr Cast Iron Downpipes, 75mm- 2.1 - m/hr Cast Iron Guttering, 75mm- 2.5 - m/hr Cast Iron RWP Fittings, 75mm- 2.2 - no/hr Aluminium Downpipes, 72mm- 2.5 - m/hr Aluminium Guttering, 72mm- 2.9 - m/hr Aluminium RWP Fittings, 72mm- 1.9 - no/hr
1 entrySource page: Rainwater Works
Subjects on this page
| Activity | Entry (verbatim) | Source |
|---|---|---|
| Guttering & Pipes | DownPipes 75 mm UPVC Pipes 3.3 m/hr 75 mm Cast Iron Pipes 2.1 m/hr 72 mm Aluminium Pipe System 2.5 m/hr Guttering 75 mm UPVC Gutter 3.1 m/hr 75 mm Cast Iron Gutter 2.5 m/hr 72 mm Aluminium Gutter System 2.9 m/hr Fittings A composite rate has been calculated to be used as an extra-over basis for all pipe fittings etc. 75 mm UPVC Fittings 3.1 no/hr 75 mm Cast Iron Fittings 2.2 no/hr 72 mm Aluminium Fittings 1.9 no/hr9 rate statements found; left for an editor | Guttering & Pipes |
1–1 of 1
These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.