Sheeted Roofs

Sheeted Roofs entries
ActivityEntry (verbatim)ValueSource
Asbestos Roofs Asbestos Type Roofs A typical rate of 39 m2/day39 m2 per dayper dayParsedAsbestos Roofs
Profiled SheetingProfiled Sheeting Systems Usually carried out with a minimum of a 2 man gang. Large Roof Areas = 54 m2/day54 m2 per dayper dayParsedProfiled Sheeting
Sheeted RoofsSheeted RoofsTask / DescriptionSlow Ave Fast Units PVC Sheeted Roofs, large areas- 50.0 - m2/day PVC Sheeted Roofs, small areas- 40.0 - m2/day Plastic Profiled Sheet Systems- 54.0 - m2/day—Sheeted Roofs

1–3 of 3

These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.