Slurry & Soil Mix Walls

Slurry & Soil Mix Walls entries
ActivityEntry (verbatim)ValueSource
Slurry Mix WallSlurry mix wall (for noise restrictions/obstructions) grab excavation to full depth, fill with cement or bentonite mix, drop and hold sheet piles in place.Excavation 1 panel (4.5 m long on plan) with grab and crane.Excavate 1 panel in 2 days + 1 day bentonite and sheet pile, giving a rate of 1 - 1.5 m/day.Therefore, once started 2 - 2.25 m/day is expected.Slurry Mix WallsTask / DescriptionSlow Ave Fast Units Crane grab, cement/bentonite and sheet piles1.8 2.5 3.4 m/day3 rate statements found; left for an editor—Slurry Mix Wall
Soil Mix WallsSoil Mix Walls...Task / DescriptionSlow Ave Fast Units Three Auger Drill, cement and cure3.8 4.5 6.4 m/day6.4 m per dayper dayParsedSoil Mix Walls

1–2 of 2

These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.