Rates, Norms & Durations / Building & Construction / Foundation Works
Slurry & Soil Mix Walls
2 entriesSource page: Slurry & Soil Mix Walls
Subjects on this page
| Activity | Entry (verbatim) | Value | Source |
|---|---|---|---|
| Slurry Mix Wall | Slurry mix wall (for noise restrictions/obstructions) grab excavation to full depth, fill with cement or bentonite mix, drop and hold sheet piles in place.Excavation 1 panel (4.5 m long on plan) with grab and crane.Excavate 1 panel in 2 days + 1 day bentonite and sheet pile, giving a rate of 1 - 1.5 m/day.Therefore, once started 2 - 2.25 m/day is expected.Slurry Mix WallsTask / DescriptionSlow Ave Fast Units Crane grab, cement/bentonite and sheet piles1.8 2.5 3.4 m/day3 rate statements found; left for an editor | — | Slurry Mix Wall |
| Soil Mix Walls | Soil Mix Walls...Task / DescriptionSlow Ave Fast Units Three Auger Drill, cement and cure3.8 4.5 6.4 m/day | 6.4 m per dayper dayParsed | Soil Mix Walls |
1–2 of 2
These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.