Slurry Mix Wall
In the Open Standard
Started by Technical Development ·
- Last updated
- Updated
- Views
- 7 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Slurry mix wall (for noise restrictions/obstructions) grab excavation to full depth, fill with cement or bentonite mix, drop and hold sheet piles in place.
Excavation 1 panel (4.5 m long on plan) with grab and crane.
Excavate 1 panel in 2 days + 1 day bentonite and sheet pile, giving a rate of 1 - 1.5 m/day.
Therefore, once started 2 - 2.25 m/day is expected.
Slurry Mix Walls
| Task / Description | Slow | Ave | Fast | Units |
| Crane grab, cement/bentonite and sheet piles | 1.8 | 2.5 | 3.4 | m/day |