Internally

2 coats emulsion - to plaster 8.00 m2/hr - to brick/blockwork 6.00 m2/hr 1 mist, 2 emulsion - to plaster 6.00 m2/hr - to brick/blockwork 4.50 m2/hr 1 primer, 1 undercoat, 1 gloss - to plaster 2.30 m2/hr Undercoat - to door frame 20.00 m/hr Gloss - to door frame 16.50 m/hr Undercoat - to door 7.14 m2

Started by Oliver Melling ·
Last updated
Updated
Views
6 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

2 coats emulsion

- to plaster 8.00 m2/hr

- to brick/blockwork 6.00 m2/hr

1 mist, 2 emulsion

- to plaster 6.00 m2/hr

- to brick/blockwork 4.50 m2/hr

1 primer, 1 undercoat, 1 gloss

- to plaster 2.30 m2/hr

Undercoat

- to door frame 20.00 m/hr

Gloss

- to door frame 16.50 m/hr

Undercoat

- to door 7.14 m2/hr

Gloss

- to door 6.25 m2/hr

 