Weather
In the Open Standard
FG
Forum GuestMember for 17 years 8 months
- Created
- 11
- 3
0
11 replies
Oldest first- 0PHPaul Harris ·Inclement weather is normally defined in a contract or other agreement under which work is conducted and when the threshold for inclement weather is met work is suspended and after a period of time the work force affected by the status is sent home and in extreme cases the site may be abandoned. Work restart may also be defined.
I do not think weather defined as "Excessively Inclement Weather" is normally relevant, irrespective of what country. The issue is if the weather inclement or it is not.
It is similar to being excessively pregnant, you are either pregnant or not.
It could be therefore that the amount of time lost due to Inclement Weather is out of the scope of the contract or agreement and could be a cause for variations outside the contract. Then the terms such as "Act of God" etc come into play.
Regards
Paul E Harris
- 0DBDavid Bordoli ·Andy Mitchell, who started this thread, was correct in his use of the term execessive’. In the most used standard form of contract one can only get an extension of time for excessively inclement weather, not just inclement weather. It’s obvious really that it gets cold and rains or snows in the winter and sometimes (in the UK!) it gets hot too.
As Ronald suggests knowing the amount of normally inclement weather (like for instance how many days of snow lying on the ground when the temperatures are less than 4C) is the starting point and those sort of figures should be factored into activity durations and logic at the onset. Only if the weather is exceptionally inclement, that is, if more days than could normally be expected, occurred then an extension of time is possible.
This, however, isn’t the end of the storey. For instance what about an activity that was scheduled to be carried out in the summer but was delayed to the winter by actions of the client? Some would argue that any stoppages due to inclement weather (as compared to the originally planned period of carrying out the work) should be allowed.
There are also various formula around that help to say which days of the inclement weather were the ‘usual’ ones and which were the excessive ones.
Andy… maybe you might want to contact me to discuss this a bit more.
Best regards
David
dbordoli@burofour.co.uk
Visit Buro Four’s NEW website
www.burofour.co.uk
- 0DBDavid Bordoli ·
Hot Weather
Nestor...
The hottest, exceptional, recent summer in the UK (I know its not hot by a lot of places standards) was in 1976 and there were claims then for delays and disruptions caused by the weather. Mainly as a result of not being able to carryout big concrete pours. The UK industry isnt reaaly geared up for producing concrete with chilled water and chilled agregates... I feel there may be some claims surfacing due to the recent spell of uncharacteristically hot UK weather.
Dictionary definitions, on the web at least are a little facile, but I think the most accurate is "(of weather of climate) physically severe". I would agree that most would immediately think of physically severe as meaning wet/cold/windy but after a little consideration I think extreme heat is also physically severe.
David
dbordoli@burofour.co.ok
visit Buro Fours NEW website
http://www.burofour.co.uk - 0TRTomas Rivera ·Nestor:
I live in the hottest (temperature wise, unfortunately) city (not the hottest place) in Mexico. During the worst summers temperature gets up to 125° F, usually fairly dry, but some summers have been very humid too, up to 90% RH. Normal temperature ranges from 100 to 120° F. When we are below 100° it is considered a "cool" day. You do not want to be here during the summer. We still do construction with some special measures.
We do not usually do claims on hot whether because it is part of our lives here. But in your case, besides proving that you had abnormally hot days, you should demonstrate how it affected your work.
Concrete work is a good example. For some pours we just do it very early in the morning or at evenings. We also need to shade them and keep them cool. But for critical pours, like slab work, we work at night. Our pour might start at 8:00 PM when everything is a little bit cooler, we make sure the ground supporting the slab is moist enough. We stop pouring about 3 or 4 in the morning. We finish the concrete surface, and we saw the joints and then apply a curing compound, wet the whole area and cover everything with burlap or a fabric just before we see the sun. We keep the slab wet for 6 days. There is an ACI (American Concrete Institute) standard about hot wheather concreting (I do not recall the exact name). You need to base your case on an industry or professional organization recommendations.
Another example is manual work on the outside under the sun rays. First, you need to be accustomed to this weather; and, you simply cannot work all day long in this conditions. Not mentioning the production rate of the worker, he wont be able to work properly after 11 or 12 noon outside a shade. For some work that is suitable, for example building exterior work, you work on one side of the building when it is shaded by the position of the sun, and after lets say lunch, you work on the other side of the building. Your workers need to have good health, eat well and have plenty of water to drink, and sometimes you have to give them what we call salt tablets for the heavy loss of minerals through sweating. Work under a shade, or inside a building is acceptable but dificult. You need to be a local to be able to work under this conditions. Some subcontractors start working early in the morning and work a short shift. Some work an evening shift. But the early shift 8 hours a day is normal for most people. What standard can you use to support your case? I am not sure at this very moment.
I am not sure if this enlightened your perspective. If you have questions or comments, I would be glad to answer.
Tomas Rivera
Altek System
Scheduling for high performance
construction projects
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?