Inclement Weather EOT
In the Open Standard
Nestor PrincipeMember for 23 years 3 months
- Created
- 11
- 4
0
Dear All,
Hope this case will attract the attention of everybody to share their won opinion.
Say...
The contract allows EOT due to inclement weather on condition that no prolongation cost will be paid. If an EOT is granted and within the said extension an inclement weather has occured, would the contractor be entitled to prolongation cost for the inclement weather delay within the EOT period. I would like to look at it as similar to incidental Sundays and holidays where prolongation cost is being paid.
Thanks to your opinion.
Regards,
Nestor
Hope this case will attract the attention of everybody to share their won opinion.
Say...
The contract allows EOT due to inclement weather on condition that no prolongation cost will be paid. If an EOT is granted and within the said extension an inclement weather has occured, would the contractor be entitled to prolongation cost for the inclement weather delay within the EOT period. I would like to look at it as similar to incidental Sundays and holidays where prolongation cost is being paid.
Thanks to your opinion.
Regards,
Nestor
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?