Variations 51.1
In the Open Standard
Razi KhanMember for 22 years 4 months
- Created
- 3
- 1
0
Hi,
FIDIC 1987
Variations: Clause 51.1 (b) omit any such work (but not if the omitted work is to be carried out by the Employer or by another contractor).
What is the Interpertation, explanation or consequence of above Clause ?
The Contractor must be compensated for the omitted work if it is carried out by Employer or by other Contractor.
What is the basis of above interpertation ?
What is the crieteria for "compensation" ? If it is the OH&P portion of price analysis of Unit Rate than what is the basis ?
I hope I am not confusing !
Thanks,
Cheers,
FIDIC 1987
Variations: Clause 51.1 (b) omit any such work (but not if the omitted work is to be carried out by the Employer or by another contractor).
What is the Interpertation, explanation or consequence of above Clause ?
The Contractor must be compensated for the omitted work if it is carried out by Employer or by other Contractor.
What is the basis of above interpertation ?
What is the crieteria for "compensation" ? If it is the OH&P portion of price analysis of Unit Rate than what is the basis ?
I hope I am not confusing !
Thanks,
Cheers,
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?