HOW VARIATIONS CAN BE CLAIMED?
In the Open Standard
Francis Moyalan, PMP,PMI-SPMember for 21 years 8 months
- Created
- 4
- 3
0
HI,
THIS IS REGARDING THE STANDARD SYSTEM TO BE FOLLOWED FOR CLAIMING A VARIATION----
CONTRACTOR’S STAND-
1.IF ANY WORK IS COMING OTHER THAN THE CONTRACT (BOQ), THEN IT HAS TO BE INSTRUCTED BY THE ENGINEER TO CARRY OUT THE JOB.
2.ENGINEER MUST BE GIVING A LETTER ASKING CONTRACTOR TO FURNISH THE DETAILED COST BREAK DOWN FOR THE XTRA WORKS
3.LATER AFTER REVIEW , THE CLAIM SHOULD BE APPROVED AND VARIATION ORDER NEED TO BE ISSUED.
ENGINEER’S STAND-
1. ADDITIONAL WORK WILL ONLY BE INSTRUCTED.
2.NO LETTER WILL BE ISSUED, ASKING TO FURNISH THE COST BREAK DOWN.(SAYS CONTRACTOR MUST BE IDENTIFYING THE VARIATION FROM THE ORIGINAL CONTRACT(BOQ)).
KINDLY PUT DOWN YOUR RESEPECTED VIEWS ON THIS, SO THAT THE SITUATION CAN BE ATTENDED PROFESSIONALY,
CHEERS,
FRANCIS V
THIS IS REGARDING THE STANDARD SYSTEM TO BE FOLLOWED FOR CLAIMING A VARIATION----
CONTRACTOR’S STAND-
1.IF ANY WORK IS COMING OTHER THAN THE CONTRACT (BOQ), THEN IT HAS TO BE INSTRUCTED BY THE ENGINEER TO CARRY OUT THE JOB.
2.ENGINEER MUST BE GIVING A LETTER ASKING CONTRACTOR TO FURNISH THE DETAILED COST BREAK DOWN FOR THE XTRA WORKS
3.LATER AFTER REVIEW , THE CLAIM SHOULD BE APPROVED AND VARIATION ORDER NEED TO BE ISSUED.
ENGINEER’S STAND-
1. ADDITIONAL WORK WILL ONLY BE INSTRUCTED.
2.NO LETTER WILL BE ISSUED, ASKING TO FURNISH THE COST BREAK DOWN.(SAYS CONTRACTOR MUST BE IDENTIFYING THE VARIATION FROM THE ORIGINAL CONTRACT(BOQ)).
KINDLY PUT DOWN YOUR RESEPECTED VIEWS ON THIS, SO THAT THE SITUATION CAN BE ATTENDED PROFESSIONALY,
CHEERS,
FRANCIS V
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?