Not in baseline asking for EOT
In the Open Standard
Santhosh kumar NarayananMember for 20 years 2 months
- Created
- 8
- 3
0
Hi Pals
I Have a doubt.
Our contractor requested for EOT of 195 days due to changes in design and other additional works, after evaluation i recommended 96 days only, even though they approved the VO but they reserve their right to adk for more.
The main concern in baseline there was no procurment activity in baseline direct link between FS with aprroval of material, (Later only surfuced up this) since there was enough time between approval & installation I haveapproved the baseline.
SInce the project got delayed and late in approval and also changes in material. Since procurment acitity is not in original baseline i have rejcted thier calim for additional duration of 2 months for procurment.
They mentioned that it is a pure human error that not included in baseline. What to do.
I Have a doubt.
Our contractor requested for EOT of 195 days due to changes in design and other additional works, after evaluation i recommended 96 days only, even though they approved the VO but they reserve their right to adk for more.
The main concern in baseline there was no procurment activity in baseline direct link between FS with aprroval of material, (Later only surfuced up this) since there was enough time between approval & installation I haveapproved the baseline.
SInce the project got delayed and late in approval and also changes in material. Since procurment acitity is not in original baseline i have rejcted thier calim for additional duration of 2 months for procurment.
They mentioned that it is a pure human error that not included in baseline. What to do.
8 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?