AACE Source Validation Protocol
In the Open Standard
Carlos AranaMember for 17 years 4 months
- Created
- 12
- 3
0
Good day!
I’m following AACE’s recomended practice for "Forensic Schedule Analysis", (You can find it at http://www.aacei.org/technical/rp.shtml)
in the Source Validation Protocol (2.1.B.8) reads:
"Ensure that the calendars used for schedule calculations reflect actual working day constraints and restrictions actually existing at the time when the baseline schedule was prepared"
I’m using Primavera P3, got the following questions:
1. How do I know the work hours per day?
2. The calendar is 7-day workweek. I understand that it is easyer to use 7-day workweeks when planning since they reflect exactly the days between a date and another. But in the field, they work 8 hours from monday to friday, and 5 hours the saturdays.
Then I know the calendar used for schedule calculations does not reflect actual working days.
How I should procceed?
I’m following AACE’s recomended practice for "Forensic Schedule Analysis", (You can find it at http://www.aacei.org/technical/rp.shtml)
in the Source Validation Protocol (2.1.B.8) reads:
"Ensure that the calendars used for schedule calculations reflect actual working day constraints and restrictions actually existing at the time when the baseline schedule was prepared"
I’m using Primavera P3, got the following questions:
1. How do I know the work hours per day?
2. The calendar is 7-day workweek. I understand that it is easyer to use 7-day workweeks when planning since they reflect exactly the days between a date and another. But in the field, they work 8 hours from monday to friday, and 5 hours the saturdays.
Then I know the calendar used for schedule calculations does not reflect actual working days.
How I should procceed?
12 replies
Oldest firstLog in or join to reply