Resource maximum limit

Giji ThomasMember for 20 years 2 months
Created
1
1
0
Is there any way to increase the limit of Resource?

In p3 DATA- Resource window, 1-3, only 5 digits can apply.

Eg. 1 - 19999
2 - 29999
from 3 to 9 only 4 digits - 3999, 4999, 5999
4 - 4999

If anybody noticed, pls help me

1 reply

Oldest first
  1. 0
    John Lawson ·
    Hi

    I am not sure if this is the correct answer.

    The max resource level in P3.1 is 9999, that is for each particular resource specified.

    If you are above this level, then try splitting the resouces into say two groups, i.e. labourers A & Labourers B, this would give the possibility of 19998 as a max.

    regards

    John