dd in baseline different then start of the project.
In the Open Standard
Mimoune DjouallahMember for 20 years
- Created
- 5
- 3
0
hi all.
our subcontractor has submitted a new revision of the baseline(it is a fast track project, he did not got all the drawing at the beginning of the project), normally there is no problems with it, as it respect the contract key dates.
but, i am not comfortable with practice to put actual dates on a baseline program, even the work has been done. i prefer always to see data date coincide with project start, we can always simulate the actual dates by relations.
so what do you think, is it no harm to do that ?, perhaps i am been too formal here.
thanks for you answers.
our subcontractor has submitted a new revision of the baseline(it is a fast track project, he did not got all the drawing at the beginning of the project), normally there is no problems with it, as it respect the contract key dates.
but, i am not comfortable with practice to put actual dates on a baseline program, even the work has been done. i prefer always to see data date coincide with project start, we can always simulate the actual dates by relations.
so what do you think, is it no harm to do that ?, perhaps i am been too formal here.
thanks for you answers.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?