EOT preparation with a very simple baseline programme.
- Created
- 4
- 4
We need to prepare an EOT claim for a project completed almost 3 years ago.
The project is a podium of 3 towers. The podium is divided into 4 parts, and each part has 4 levels. Each part has an area of around 7000 ~ 9000 sq. meters per level. It is enclosed by a non-load bearing wall, floor to floor. Each part has its own contract completion date.
In the baseline programme, yes it is divided into 4 parts. But the consruction of each level was shown in one activity/bar only. It is like, Construct Level 1, then SS+lag Construct perimeter wall to Level 2, then SS+lag Construct Level 2, and so on.
But ofcourse on site, each level was not casted in one go, they divided and did it in portions. And each portions has its own reason for delay.
We have a monthly update of the baseline programme, but it is like putting the percent completed up to he data date and no break-down for each level into portions, the way they did it.
We also have some correspondence and records for some of the delay for a particular portion.
So what do you think is the best way to prepare an EOT giving the information and record we have.
One guy told me to make a corrected baseline programme in which I will break-down the activities in the original baseline programme.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?