LD risk for late start but completion on time
- Created
- 1
- 3
Hi,
I have one question.
I am working on a building project with many nominated sub contractor by main contractor
If I did not start my construction on time as per client master programme, but I can finish my job on time or earlier. Am I liable for LD ? Bear in mind that my delay or late start has a signiificant impact on other contractor who are my successor and their rate of progress cannot keep up with me. Thus my late start could hinder the completion of the entire project on time.
There's no key milestone in contract and no proper update of master programme from main contractor.