CE's on NEC3
In the Open Standard
Oliver MellingMember for 19 years 5 months
- Created
- 5
- 2
0
I have 3 CE's on a project that have been accepted by the PM as having an effect on the price and consequently increased the target price,but they were never impacted on the accepted schedule at the time of being agreed.
Errors in the previously accepted programme have now been rectified and the newly accepted schedule now puts tasks associated with one of the CE's on the critical path. To assess its impact on the LD date and any key dates, is it acceptable to do the analysis on the newly accepted programme? Or does it need to be in-line with the contract against the last accepted programme prior to the CE being raised?