Methodology

Stephen HepburnMember for 23 years 4 months
Created
0
3
0

Has anyone heard of an As-Is Methodology.

Using progress only update data, with an option to modify when (as built) dates do not match( progress update ) critical activities dates.

I try and stick to the guidelines a reference with the SCL protocol, and 29r-3, so never heard of this used before, as it seems too manipulative, requiring more substantiation.

Any thoughts