Methodology
In the Open Standard
Stephen HepburnMember for 23 years 4 months
- Created
- 0
- 3
0
Has anyone heard of an As-Is Methodology.
Using progress only update data, with an option to modify when (as built) dates do not match( progress update ) critical activities dates.
I try and stick to the guidelines a reference with the SCL protocol, and 29r-3, so never heard of this used before, as it seems too manipulative, requiring more substantiation.
Any thoughts
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?