EOT Evaluation
In the Open Standard
Tim TamMember for 13 years 5 months
- Created
- 2
- 1
0
Hi,
Must I use TIA, IAP, APAB, CAB to do EOT claim and evaluation ?
If I can prove the delay not using the above method, will it be acceptable ?
I'm not using P6 but Microsoft project, all I need is to identify the critical path from the programme and put in the actual start and finish date of delay into the activities, it will change the end date of the whole program. the difference from the baseline end date and new date will be the delay impact. to me is as simple as that.