EOT Evaluation

Tim TamMember for 13 years 5 months
Created
2
1
0

Hi,

Must I use TIA, IAP, APAB, CAB to do EOT claim and evaluation ?

If I can prove the delay not using the above method, will it be acceptable ?

I'm not using P6 but Microsoft project, all I need is to identify the critical path from the programme and put in the actual start and finish date of delay into the activities, it will change the end date of the whole program. the difference from the baseline end date and new date will be the delay impact. to me is as simple as that.

2 replies

Oldest first
  1. 0
    Johannes Vandenberg ·

    Hi Tim TamMike Testro has

    Hi Tim Tam

    Mike Testro has exellent tutorials on this subject. 

     

    Regards Johannes

  2. 0
    Mike Testro ·

    Hi Tim TamWhat you have

    Hi Tim Tam

    What you have described is an Impacted as Planned delay analysis.

    I have prepared a YES / NO flow chart to assist in the decision of what analysis method to use for delay analysis.

    Send me a message with your email and I will forward it to you.

    Best regards

    Mike Testro