Displaying delay of tasks graphically

Ijaz AhmadMember for 20 years 3 months
Created
3
3
0
Hi guys,
Will anybody tell me how can we display the delay of tasks graphically, especially on critical path?
Thanks

3 replies

Oldest first
  1. 0
    Andrew Dick ·
    Ijaz,
    I would use either the original baseline bar and the current bar on the GANTT or see if you can create a special bar by using user_start_date fields filtered on critical activities in conjunction with a global change.

    You could populate the start date with the baseline start/finish, and the finish date with the actual/planned start/finish.

    Andy
  2. 0
    Oliver Melling ·
    I agree, baseline and the current bar on the Gantt is the best way.
  3. 0
    Patricia Le Clainche ·

    I also agree.
    But, what about Technical % complete on a task. Do someone use this data on GANTT chart?

    Kindest regards.
    Patricia