Skip to content

Delay

Rohit RangnekarMember for 17 years 4 months
Created
0
1
0
Dear Sir,

In case of activity getting delayed , a solution comes out that for the remaining duration left , you have to increase 1nos. manpower. Can at this point of time a new resource can be added to activity , if yes then how ?

Regards,

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?