Is there a technical name for delay caused by not being able to work as scheduled? for example if something is FS instead of SS?
In the Open Standard
John ReevesMember for 13 years 5 months
- Created
- 3
- 3
0
Is there a technical name for delay caused by not being able to work as scheduled? for example if something is FS instead of SS? (for example thought could start steel same time as concrete but had to wait until done.) "Out of Sequence Delay" or "Logic Error Delay" or "Planning Delay"?