Is there a technical name for delay caused by not being able to work as scheduled? for example if something is FS instead of SS?

John ReevesMember for 13 years 5 months
Created
3
3
0

Is there a technical name for delay caused by not being able to work as scheduled? for example if something is FS instead of SS? (for example thought could start steel same time as concrete but had to wait until done.)  "Out of Sequence Delay" or "Logic Error Delay" or "Planning Delay"?

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    any one of those is

    any one of those is sufficent 

  2. 0
    Alex Lyaschenko ·

    If a schedule has SS instead

    If a schedule has SS instead of FS (or any other combination) it is just a schedule quality issue that only could be solved by maturing schedule development process. 

  3. 0
    Alex Lyaschenko ·

    If a schedule has SS instead

    If a schedule has SS instead of FS (or any other combination) it is just a schedule quality issue that only could be solved by maturing schedule development process. 