Planned Value Labour Unit
In the Open Standard
Chetan RanderiaMember for 16 years 8 months
- Created
- 7
- 2
0
Planned Value Labor Unit at the header level for group of activities (Grouped by Supervisor ) is not matching with same group of activities when selected / Highlighted with resource curve . The variations is more than 3 % of Budgeted value . Why this two value are different , could anybody explain. ??? . If I see the definitions of Planned Value Labor Unit it says “ The curve distributions is additionally factored into calculations” . Can anybody explain from where is additional factor coming ???
7 replies