Skip to content

Planned Value

Dinesh Kumar DamavarapuMember for 24 years 7 months
Created
1
2
0
Dear Experts,

I am currently facing an issue with one our programmes which was submitted by the contractor. This is an update, we have assigned the accepted baseline to it. As you might aware, the planned value can be viewed in a column which is a cumulative figure and also periodically in a table. These two values just before the data date should match but in this programme they are not matching. I tried to find out the reason for it but failed and I would appreciate if you advice the possible reason.

thanks & regards

Dinesh

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Dinesh,
    Of course Plan Value will keep changing once you update the Project. Plan Value will not change if you have assigned a baseline and use BL Plan Value. For current project all activities that not happened on the plan date will move after the data date therefore the plan values will also move. The use of baseline is to compare what has been targeted vs the current. Current Plan Value will become a forecast to complete.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?