Missing Row when P6 Exported to MS Project

Leonard EsberMember for 13 years 3 months
Created
2
4
0

Dear colleagues,

I'd exported a project from P6 R8.2 to MS Project, but the row from P6 that shows project name, total duration of project, start and projected finish date of project doesn't appears in MS Project format.

I look forward you could help me with this.  Thank you.

Regards.

2 replies

Oldest first
  1. 0
    Paul Harris ·

    To Options, go to the Project

    To Options, go to the Project Options and display the Project Summary bars, or add the bar by creating a summary bar.

    Regards

    Paul E Harris
    BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner
    Managing Director and President
    Eastwood Harris Pty Ltd, Australia
    www.eh.com.au,  www.eastwoodharris.com, www.primaskills.com.au  and www.primavera.com.au
    Project Control Consultants and Planning and scheduling software book and training material publishers

  2. 0
    Leonard Esber ·

    Thank you very much.  But

    Thank you very much.  But this is what happened I did...from menu bar, I clicked TOOLS then OPTIONS then VIEW tab.  Under Outline options for '(project name)' I checked the box Show project summary tasks then the uppermost row appeared.

Log in or join to reply