Budget quantity for milestones

Eckart SchenckMember for 21 years 4 months
Created
1
1
0
Hi all,

I’m trying to put a quantity onto a milestone (purchase order).
This works fine for actual MS, but not for planned.

Do you know reason for that, is there a way around that?

Thanks for your help!

Heinz

1 reply

Oldest first
  1. 0
    Gordon Blair ·
    Umm have you tried just adding it into the cost window?

    Resource ’What ever you want to call it’

    Budgeted Cost ’how much it is’

    As long as you’ve got the relevant resource in the dictionary, doesn’t appear to cause a problem.

    This is how I do all my Milestone payments.

    Let me know how you get on?

    Cheers

    Gordon