Skip to content

Installed Quantity for physical % complete

Dylan Wan, PMP EVPMember for 21 years 7 months
Created
3
1
0
Is there a way to track the planned quantity to be installed and quantity actually installed for an activity?

Bascally we want to derived the percent complete based on the quantity installed / planned quantity. The actual quantity installed can be pulled from our production system.

3 replies

Oldest first
  1. 0
    Anand Kulkarni ·
    Hi Wan,

    In Tools/Tabular Reports/Resource/Earned Value

    The out put is detailed Resource wise % complete Actual Qty. of Work Performed (ACP), Budgeted qty. of Work Scheduled (BCWP), Budgeted qty. of work scheduled(BCWS, Variance & At completion quantities

    cheers,

    Anand
  2. 0
    Dylan Wan, PMP EVP ·
    Thanks for your reply, Anand.

    Is the planned quantity entered as budgeted quantity in the resource window?

    Can I have an activity level quantity? We have multiple resources assigned to the same activity.
  3. 0
    Anand Kulkarni ·
    Dear Wan,

    Yes Planned quantities are the budgeted quantities only.

    Yes the report gives you resource wise break-up for all the activities with the summary of resources.

    Multiples resoures to one activitiy is not an issue at all.


    cheers

    anand

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?