Installed Quantity for physical % complete
In the Open Standard
Dylan Wan, PMP EVPMember for 21 years 7 months
- Created
- 3
- 1
0
Is there a way to track the planned quantity to be installed and quantity actually installed for an activity?
Bascally we want to derived the percent complete based on the quantity installed / planned quantity. The actual quantity installed can be pulled from our production system.
Bascally we want to derived the percent complete based on the quantity installed / planned quantity. The actual quantity installed can be pulled from our production system.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?